CALIBRATING PROCEDURE
1. Insure the unit has a vacuum before you
begin calibrating procedures. If unit requires
venting refer to Kettle Venting Instructions on
page 17 of this manual.
2. Turn kettle on and set temperature dial to 10
(Max.).
3. Allow the unit to cycle twice.
4. Check temperature of the inner kettle surface
with a digital surface thermometer.
5. Temperature should be between 260° F and
265° F.
6. Using a screw driver adjust temperature by
turning the potentiometer on the black box.
Turn very little. Turn clockwise to INCREASES
and counter-clockwise to DECREASE
temperature.
7. Allow the unit to cycle twice.
8. Check temperature of the inner kettle surface
with a digital surface thermometer.
9. Repeat steps 4 through 8 until unit is calibrated.
PRESSURE RELIEF VALVE
TESTING PROCEDURE
The pressure relief valve must be checked at least
twice a year as part of the normal maintenance
performed.
1. With the kettle empty, turn unit ON and set
temperature control knob to 10 (Max.). Allow the
kettle to heat until the unit cycles off.
2. Switch unit OFF and disconnect main power at
fused disconnect switch.
3. Remove bottom cover.
4. Stand to the side of the pressure relief valve
discharge tube and pull valve open for a
maximum of one second. Repeat test three to
four times. Each time the mechanism should
move freely and be accompanied by a rapid
escape of steam
WARNING
Kettle will be hot. Use gloves for protection.